Details of navigation restrictions for Environment Agency waterways
Below are the EA locks due to be closed this winter, and details of the work to be carried out on them…
Rushey – 8 January 2007 to 16 February 2007
Lock gate re-sheet
Shifford – 20 November 2006 to 22 December 2006
Lock gate re-sheet
Pinkhill – 6 November 2006 to 19 January 2007
New lock gates
Osney – 6 November 2006 to 23 February 2007
New lock gates
Iffley – 6 November 2006 to 24 November 2006
Lock gate re-sheet
Abingdon – 27 November 2006 to 15 December 2006
Out of hours power
Clifton – 1 November 2006 to 23 February 2007
New tail layby and head lock cut bank protection
Days – 1 November 2006 to 2 March 2007
Lock wall and walkway refurbishment
Benson – 2 October 2006 to 13 October 2006
New lock gate walkways – restricted access
Mapledurham – 15 January 2007 to 23 March 2007
New pedestrian footbridge and repairs to tail bullnoses
Caversham – 6 November 2006 to 24 November 2006
Out of hours power
Marlow – 1 November 2006 to 15 December 2006
Lock gate re-sheet
Boulters – 1 November 2006 to 21 December 2006
& 8 January 2007 to 9 February 2007
Improvements to egress steps
Bray – 1 November 2006 to 23 March 2007
Head bank protection and extension to head layby. Improvements to tail layby and canoe portage
Penton Hook – 1 November 2006 to 16 February 2007
Lock wall refurbishment
Chertsey – 1 November 2006 to 21 December 2006
& 8 January 2007 to 9 February 2007
Tail lock cut retaining wall refurbishment and new raised layby
Shepperton – 20 November 2006 to 1 December 2006
Replacement lock gate anchor plates
Molesley – 8 January 2007 to 23 February 2007
Lock gate re-sheet
Teddington launch lock only – 1 February 2007 to 31 March 2007
Lock island retaining wall and bank protection
More information can be found here.